Campus Construction Continues
by George Zamora
SOCORRO, N.M., April 19, 1999 -- Thanks to last year's
passage of the state General Obligation (GO) Bond, a major construction
project at New Mexico Tech will be completed on time later this
summer, while another is scheduled to soon get underway.
The university received nearly $2.5 million to complete construction
of the second and third floors of the Jones Hall addition (which
is scheduled for completion in the first week in August) and also
was allotted about $3.5 million of GO Bond monies to begin the
Cramer and Weir halls renovation project.
Another $930,000 from the GO Bond also has been allocated
as infrastructure money for New Mexico Tech, providing the university
with a new student database with roughly half of that total, while
the other half goes to improvements and upgrades to campus lighting,
water and gas lines, and roads, as well as a mechanical refurbishment
of the Kelly Building, which houses the Petroleum Recovery Research
Center (PRRC).
An additional $54,000 of the GO Bond monies Tech received
have been earmarked for various projects associated with complying
with the American with Disabilities Act (ADA).
The Jones Hall addition is a $7.8 million three-story building
which will provide an additional 44,000 square-feet of space for
classrooms, laboratories, and offices on campus.
The New Mexico Tech biology and environmental engineering
departments will become the tenants of the new building shortly
after its completion, sometime before the start of the 1999 fall
semester.
The renovation of Cramer and Weir halls, however, currently
remains on hold because of the uncertainty surrounding the state's
budget for the next fiscal year. The Cramer and Weir project had
been given the highest priority of all the state's educational
capital projects under the scope of the New Mexico Commission
on Higher Education's facilities committee.
The $2.8 million needed to complete funding for the Cramer
and Weir renovation is still pending legislative action.
Notwithstanding the current uncertainty surrounding state
budgets, plans are continuing at New Mexico Tech for the Cramer
and Weir renovation, as well as other campus building projects.
When the Jones Hall addition is completed, construction is
scheduled to begin on a new $4 million residence hall complex
which will provide 144 more beds for Tech students who choose
to
live on-campus, probably in time for the start of the 2000 fall
semester.
Presidents Hall, one of the older dorms on campus, eventually
will be retired in its established role as a residence hall and
will be modified to accommodate departmental offices being temporarily
displaced during the complete makeover of Cramer and Weir halls.
When renovation of Cramer and Weir is completed, Presidents
will continue to house other academic offices and provide additional
student space.
The construction on campus won't slow up with these project's
finish: there are plans on the drawing board for a new Student
Union Building and other facilities at New Mexico Tech to begin
construction sometime after 2000.
-NMT-
|